MIDLAND Work is scheduled to begin later this month on a project to “reverse” (relocate) ramps, add some auxiliary lanes and rehabilitate some roadway on Highway 191 and West Loop 250, a Texas Department of Transportation press release stated.
The most notable part of the project will move the eastbound Highway 191 exit ramp further west. Known as a braided ramp, the new off ramp will go over the existing on ramp.
The project is expected to be completed in mid-2023. Jones Brothers Dirt & Paving of Odessa won the project with a low bid of a little more than $18.2 million.
Ramp “reversals” are also called for in three locations as part of the project. The ramp “reversals” will occur on westbound Highway 191 between West Loop 250 and Highway 158 as well as on both service roads of West Loop 250 between Wadley Avenue and Highway 191.
The current entrance ramp locations will become exit ramp locations; likewise, the current exit ramp locations will become entrance ramp locations. The ramp reconfigurations will eliminate some merging conflict points and will also allow more room for queueing on the service road.
Other work scheduled in the project involves intersection improvements at the mid-level interchanges of Highway 191 and Loop 250. In addition to some auxiliary lanes to provide more capacity, the intersections will be built with full-depth concrete pavement to better handle wear and tear from traffic.
The roads at the signalized intersections at Highway 158 under the Highway 191 overpass will also be rebuilt.
A reduced speed limit will be in place in work areas. Motorists are asked to slow down when driving in work zones. Motorists are also reminded that state law requires them to obey any warning signs, flaggers and pilot cars encountered in the work zone. TxDOT wants everyone — motorists, contractor employees and TxDOT staff — to go home safely every day.
The first stage of work scheduled to start the week of Oct. 11 will involve widening the shoulders on Highway 191 service roads in both directions from the overpass at Highway 158 to Loop 250. Work will take place on the outside lanes of both service roads in this early stage.